Gross Point Road Project Overview

Project Overview

The 2025 Arterial Street Improvement Program consists of resurfacing Gross Point Road.

The Village of Morton Grove receives federal funding to use for construction and construction engineering on local streets. The construction improvements consist of repairing deteriorated curb and gutter and utility structures, patching deficient areas of concrete or asphalt pavement, upgrading curb ramps, milling and resurfacing asphalt surface pavement, and other incidental work needed to restore disturbed areas of the right-of-way.

Project Fast Facts:

Location

Gross Point Road from Oakton Street to Main Street

Total Distance:

2,897 feet (0.55 miles)

Project Type:

Roadway Improvements and Resurfacing

Design Speed:

30 Miles per hours

ADT (2022):

16,600 vehicles per day

The project is managed by InNova Consulting, Inc. on behalf of the Village of Morton Grove. We are committed to proactive communication and minimizing disruptions to residents and businesses throughout the construction process. Your patience and cooperation are greatly appreciated.

Project Updates :

Check back here when construction begins for construction updates and progress reports!

0 %

Gross Point

Upcoming Work Update

Upcoming Work:

  • Pavement markings to be installed in the spring season.

Project Summary

IDOT Contract Number: 61L63

The construction on Gross Point Road will consist of intermittent patching of the roadway to preserve the life of the pavement. 2-1/4”  and 1-1/2″ of asphalt binder and surface courses will be removed and replaced to improve the roadway. Curb and Gutter will be replaced as necessary. Sidewalks and Driveways requiring ADA corrections will be updated.  Pavement markings and other miscellaneous items will complete the work.

Project Schedule:

September 2025 to June 2026 – substantial completion expected November 15 – 17, 2025

Project Limits:

Oakton Street to Main Street

Traffic Control :

Traffic will be maintained in each direction throughout the construction with lane reductions. No lane closures are anticipated.

Primary Project Contacts:

Contractor:

Peter Baker & Son, Co
Consultant Engineer:
InNova Consulting, Inc.

Any questions can be answered by Mohammed Fazl Ur Rahman (Resident Engineer) at mrahman@innovaconsultinc.com or (309)-420-2833

Proposed Typical section : Proposed Limits :

Project Timeline

Project Letting
June 2025
The project will be put out for bid by the Illinois Department of Transportation (IDOT).
August to September 2025
Construction engineering services will begin, with principal work starting in the field.
Construction Start
Completion Date
Nov. 15-17, 2025 ( substantial completion )
All major contract items and roadways will be safely opened to traffic by this date.
Nov 2025 - June 2026
The contractor will complete all clean-up and punch list items within 10 working days after the completion date. The project will officially close in June 2026.
Finalization
June 2025
Project Letting
The project will be put out for bid by the Illinois Department of Transportation (IDOT).
August to September 2025
Construction Start
Construction engineering services will begin, with principal work starting in the field.
Oct, 2025 ( substantial completion )
Completion Date
All major contract items and roadways will be safely opened to traffic by this date.
Nov 2025 - June 2026
Finalization
The contractor will complete all clean-up and punch list items within 10 working days after the completion date. The project will officially close in June 2026.